According to state law senate bill 2419 no asbestos could be applied after July 1, 1976 although some ceilings applied before that are asbestos free as in the early days of acoustic the asbestos was added by the applicator and some sprayed slightly after that date, may contain asbestos as contractors ran through their stock of material We suggest if your ceiling was sprayed before 1977 taking or sending a small sample to a laboratory such as National Analytical Laboratories at 10416 Investment Circle in Rancho Cordova.916-361-0555 www.nal1.com. Simply get a small area of the ceiling wet as not to cause any dust and scrape a sample into a freezer bag. NAL will also come collect a sample for you.
Explanation of asbestos abatement procedure
We prepare your home for abatement of your asbestos containing
acoustic ceiling by covering the floors, walls, windows and
exterior doors with one layer of plastic, Once the area is
completely protected we cover the floors with two additional
layers of plastic and the walls with one additional layer of
plastic, a decontamination unit is then installed at entrance to
work area and a negative air machine is installed at other end
of work site, Fixtures are then removed from ceiling
|
|||||||||||||||||||||
|
Kevin Bussard |
John Garayalde |
Keith Martin |
All members of the abatement team have been trained by an
O.S.H.A and E.P.A approved facility at the contactor-supervisor
level and has an average of over fifteen years in the acoustic
ceiling removal and drywall refinishing industry.
All drywall is inspected for integrity and
tightness to wood framing. Any bad joint tape is replaced; all
joints and nails are coated with joint compound to achieve as
smooth a surface as possible. New wall texture is then applied.
As an option two coats of paint are then applied to provide you
a finished ceiling. The final layers of protective plastic are
then removed and work area cleaned. If you choose we will then
replace fixtures to the ceiling. Please be aware that our
masking tape will pull paint from the top of your walls and that
the new texture follows the same edge as your existing ceiling
Please be aware that during the refinishing portion of you
project We must wash our ladders and tools off outside leaving
some residue that is water-soluble, dissipates fairly rapidly
and won’t harm any plant or animals. This is asbestos free
material.
|
Joint tape replaced |
Joints and nails coated |
Imperfect smooth texture applied
|
|
Ceilings sprayed |
Ceilings backrolled |
Final plastic pulled |
In simplest terms we need the work area
clear, vacant. All cloth window coverings must be removed. If
this is an impossible task large pieces of furniture made of
wood glass or metal can remain placed against walls. For example
entertainment centers, dressers, desks and the like can remain
in the work area contents of these pieces can remain in them if
contents are protected by the furniture. Closets if not being
abated can remain full.
During the abatement process you nor anyone else will not have
access to your property. When we arrive please give our crew
leader a key or some other access to the property and a way to
contact you at the end of the abatement process. If you have any
questions or need further instructions please call us at
916-944-1711.